Commissioning
Greenstar Danesmoor Utility 2022+ and Utility System 2022+ - 6 721 846 263 (2022/01) 41
6.3 Water treatment
Ensure that the system has been cleaned. Refer to section 4.1.2 of
these instructions.
Inhibitor (Central Heating)
Check drain cocks are closed and all radiator valves are open before
adding a suitable inhibitor or combined inhibitor/anti-freeze, if the
system is exposed to freezing conditions, to the heating system
water in accordance with the manufacturers instructions.
Fill system via a WRAS approved filling loop to between 1 and 1.5
bar.
Vent all radiators; tighten vents when complete.
Re-pressurise if necessary to 1bar.
Set all controls to maximum.
Record the date when the inhibitor was added to the system in the
Boiler commissioning checklist and in the guarantee registration.
Water treatment products
Suitable water treatment products can be obtain from the following
manufacturers:
6.4 Starting the appliance
1. Check the oil supply is correctly fitted, pressure tested and in good
working order before turning on the oil supply valves to the boiler.
Turn on the main oil supply valve at the tank and draw off at least
2.5 litres of oil until a steady flow of clear uncontaminated oil can be
seen as follows:
The oil supply to the boiler should be primed before the burner is
operated to avoid unnecessary pump wear.
The use of an oil suction pump will prime and flush through any oil
supply set up simply and easily, alternatively the following
procedures can be used.
6.4.1 Single pipe gravity feed system:
Disconnect the flexible oil hose and open the isolating valve to
discharge the oil into a suitable container.
If a top entry tank has been used the pipework will need to be primed
before the oil will discharge under gravity.
When completed, close the isolating valve, reconnect the flexible oil
hose.
When the oil reaches the pump, bleed the air from the pump:
Open the isolating valve and the oil pump bleed port [1] to discharge
into a suitable container once the boiler is started up.
Switch on the electricity supply to the boiler.
Set the programmer to ON for CH and DHW.
Turn on the boiler CH control thermostat.
Allow the burner to run through to lockout .
Fig. 62
[1] Bleed and pressure gauge port
[2] Vacuum gauge connection
[3] Pressure adjuster
[4] Cover retaining screws x4
If no oil comes out of the port valve [1], then re-prime the oil line as
detailed above
Wait 2 minutes then press the lockout reset button [K].
Repeat the procedure until a steady stream of oil without air, runs
from the bleed port, then lock bleed port [1].
Switch off the boiler.
6.4.2 Double pipe sub-gravity feed systems and single pipe
suction lift with de-aerator:
Prime the oil supply pipework to prevent oil pump damage.
To prime a de-aerator [2], disconnect the flexible oil inlet hose [7]
from the isolation valve and place in a container of heating oil[6].
Connect a spare flexible oil hose [5], to discharge into container [6].
Open the isolating valve, turn on the power to the boiler and set the
programmer to ON. Prime the de-aerator until there is a steady flow
of oil into container [6]. Turn off the boiler then reconnect the
flexible oil inlet hose [7].
Turn on the boiler, set the programmer to ON and turn the room
thermostat up to create a demand for heat.
The oil level in the de-aerator will drop whilst the oil is being drawn
from the tank. If the de-aerator empties and the burner locks out
before the oil is drawn from the tank, you will have to prime the de-
aerator again.
NOTICE:
Salt based, softened water must not be used to fill
the central heating system.
The pH value of the system water must be between 6.5
and 8 or the appliance warranty will be invalidated.
NOTICE:
The concentration of inhibitor in the system should
be checked every 12 months or sooner if system
content is lost.
In cases where all attempts to find a micro leak have
failed, Worcester, Bosch Group supports the use of
Fernox F4 leak sealer.
ADEY 01242 546700 or www.adey.com
FERNOX 0330 100 7750 or www.fernox.com
SENTINEL 01928 704330 or www.sentinelprotects.com/uk
NOTICE:
Never run the appliance when the appliance/system
is unpressurised (sealed systems) or empty.
6720821683-11.1Wo
4
1
3
2
41

Hulp nodig? Stel uw vraag in het forum

Spelregels

Misbruik melden

Gebruikershandleiding.com neemt misbruik van zijn services uitermate serieus. U kunt hieronder aangeven waarom deze vraag ongepast is. Wij controleren de vraag en zonodig wordt deze verwijderd.

Product:

Bijvoorbeeld antisemitische inhoud, racistische inhoud, of materiaal dat gewelddadige fysieke handelingen tot gevolg kan hebben.

Bijvoorbeeld een creditcardnummer, een persoonlijk identificatienummer, of een geheim adres. E-mailadressen en volledige namen worden niet als privégegevens beschouwd.

Spelregels forum

Om tot zinvolle vragen te komen hanteren wij de volgende spelregels:

Belangrijk! Als er een antwoord wordt gegeven op uw vraag, dan is het voor de gever van het antwoord nuttig om te weten als u er wel (of niet) mee geholpen bent! Wij vragen u dus ook te reageren op een antwoord.

Belangrijk! Antwoorden worden ook per e-mail naar abonnees gestuurd. Laat uw emailadres achter op deze site, zodat u op de hoogte blijft. U krijgt dan ook andere vragen en antwoorden te zien.

Abonneren

Abonneer u voor het ontvangen van emails voor uw Worcester-Bosch Greenstar Danesmoor Utility Regular - Utility System bij:


U ontvangt een email met instructies om u voor één of beide opties in te schrijven.


Ontvang uw handleiding per email

Vul uw emailadres in en ontvang de handleiding van Worcester-Bosch Greenstar Danesmoor Utility Regular - Utility System in de taal/talen: Engels als bijlage per email.

De handleiding is 14.85 mb groot.

 

U ontvangt de handleiding per email binnen enkele minuten. Als u geen email heeft ontvangen, dan heeft u waarschijnlijk een verkeerd emailadres ingevuld of is uw mailbox te vol. Daarnaast kan het zijn dat uw internetprovider een maximum heeft aan de grootte per email. Omdat hier een handleiding wordt meegestuurd, kan het voorkomen dat de email groter is dan toegestaan bij uw provider.

Stel vragen via chat aan uw handleiding

Stel uw vraag over deze PDF

loading

Uw handleiding is per email verstuurd. Controleer uw email

Als u niet binnen een kwartier uw email met handleiding ontvangen heeft, kan het zijn dat u een verkeerd emailadres heeft ingevuld of dat uw emailprovider een maximum grootte per email heeft ingesteld die kleiner is dan de grootte van de handleiding.

Er is een email naar u verstuurd om uw inschrijving definitief te maken.

Controleer uw email en volg de aanwijzingen op om uw inschrijving definitief te maken

U heeft geen emailadres opgegeven

Als u de handleiding per email wilt ontvangen, vul dan een geldig emailadres in.

Uw vraag is op deze pagina toegevoegd

Wilt u een email ontvangen bij een antwoord en/of nieuwe vragen? Vul dan hier uw emailadres in.



Info