Pre-Installation
Greenstar Danesmoor Utility 2022+ and Utility System 2022+ - 6 721 846 263 (2022/01) 13
[NOTE:] The table and illustration above is a guide only and does not in
any way override the de-aerator manufacturer’s instructions
4.3.4 Pipework
Refer to the oil supply sections Single pipe gravity feed
system: 4.3.1, Double pipe sub-gravity feed system: 4.3.2 & Single
pipe suction lift with de-aerator: 4.3.3 for oil supply pipework
configurations.
Oil supply pipework considerations:
Lay the oil supply pipe as straight and level as possible to avoid air
pockets and unnecessary friction losses.
Route away from the boiler access door or other hot surfaces.
Install a manual isolating valve to the oil supply pipe, as close to the
oil storage tank as possible.
Fit an oil strainer and water separator to the oil supply pipe, near the
oil storage tank.
Fit an additional oil filter (70 μm max filtration size) close to the
boiler, but not inside the boiler casing.
Fit a fire valve in accordance with BS 5410.
The fire valve should be fitted externally to the building with the
fire valve sensor located within the appliance case.
A fire valve with a shut off temperature of 85°C or higher must be
fitted to avoid the possibility of nuisance shut offs.
A capillary type valve provides a neat and simple installation.
Alternatively, a fusible link or electrical system may be used.
Under no circumstances should a combination isolating/fire valve be
used as the sole fire protection device.
4.3.5 Boiler isolation valve
Use copper pipe of the correct diameter according to the information
shown in oil supply sections 4.3.1, 4.3.2 & 4.3.3.
If using soft copper pipe (R220) with a compression fitting, an
insert must be used to prevent the pipe from collapsing or
distorting when the fitting is tightened.
Slide nut [1] and olive [5] onto the oil supply pipe [4].
Slide insert [3] into the pipe.
Offer the pipe to the fitting [2] and tighten the nut [1].
Fig. 8 Isolation valve bracket removed for clarity
Use flexible hoses to connect to the oil pump.
4.4 Water systems and pipework
Primary system plastic pipework:
Any plastic pipework used for the CH system must have a polymeric
barrier, complying with BS 7921 and installed to BS 5955 with
1000mm (minimum) length of copper or steel pipe connected to the
boiler.
Plastic pipework used for underfloor heating must be correctly
controlled with a thermostatic blending valve limiting the
temperature of the circuits to approximately 50°C with 1000mm
(minimum) length of copper or steel pipe connected to the boiler,
and a 20K differential must be maintained at the appliance.
Primary system/connections/valves:
Do not use galvanised pipes or radiators.
All system connections, taps and mixing valves must be capable of
sustaining a pressure of 3 bar.
Radiator valves should conform to BS 2767:10.
All other valves should conform to BS 1010.
An automatic bypass valve must be connected between the heating
flow and return where TRVs are used on all radiators, fitted to give at
least a 3 metre circuit when activated.
Drain cocks are required at all the lowest points on the system.
Air vents are required at all high points on the system.
Open vent primary system (Regular only)
The open vent pipe (F) and feed and expansion pipe (H) must rise
continuously from the appliance.
The feed and expansion cistern (E) must be positioned to provide a
static head (S) of at least 1 metre above the highest point in the
heating system to the water level in the feed and expansion cistern.
Ensure adequate space is left in the expansion cistern for expansion
of the system water.
No valve shall be fitted in the open vent pipe (F) or the feed and
expansion pipe (H).
The open vent pipe (F) must be at least 22mmØ.
FUEL FLOW RATE
2.5kg/h 5kg/h 10kg/h 10kg/h
Head (m) 8mmØ 8mmØ 8mmØ 10mmØ
010055 26 100
0.5 95 45 23 100
1.0 80 40 20 90
1.5 70 35 17 75
2.0 60 30 14 65
2.5 45 25 11 50
3.0 35 15 8 35
3.5 25 10 5 20
NOTICE:
The boiler should not be allowed to operate with a
return temperature of less than 30°C when the
system is up to operating temperature.
Oil burners cannot modulate to accommodate a
reduction in heating loads. If the heating load can be
significantly reduced due to TRV’s or zoning of the
heating circuits, consideration should be given as to how
short cycling of the burner could be prevented.
Burner run times should remain greater than 2 minutes
during normal operation.
A buffer vessel or thermal store should be considered to
help prevent excessive short cycling of a single
appliance, or a low loss header could be used to divide
the heating duty between multiple lower output
appliances.
13

Hulp nodig? Stel uw vraag in het forum

Spelregels

Misbruik melden

Gebruikershandleiding.com neemt misbruik van zijn services uitermate serieus. U kunt hieronder aangeven waarom deze vraag ongepast is. Wij controleren de vraag en zonodig wordt deze verwijderd.

Product:

Bijvoorbeeld antisemitische inhoud, racistische inhoud, of materiaal dat gewelddadige fysieke handelingen tot gevolg kan hebben.

Bijvoorbeeld een creditcardnummer, een persoonlijk identificatienummer, of een geheim adres. E-mailadressen en volledige namen worden niet als privégegevens beschouwd.

Spelregels forum

Om tot zinvolle vragen te komen hanteren wij de volgende spelregels:

Belangrijk! Als er een antwoord wordt gegeven op uw vraag, dan is het voor de gever van het antwoord nuttig om te weten als u er wel (of niet) mee geholpen bent! Wij vragen u dus ook te reageren op een antwoord.

Belangrijk! Antwoorden worden ook per e-mail naar abonnees gestuurd. Laat uw emailadres achter op deze site, zodat u op de hoogte blijft. U krijgt dan ook andere vragen en antwoorden te zien.

Abonneren

Abonneer u voor het ontvangen van emails voor uw Worcester-Bosch Greenstar Danesmoor Utility Regular - Utility System bij:


U ontvangt een email met instructies om u voor één of beide opties in te schrijven.


Ontvang uw handleiding per email

Vul uw emailadres in en ontvang de handleiding van Worcester-Bosch Greenstar Danesmoor Utility Regular - Utility System in de taal/talen: Engels als bijlage per email.

De handleiding is 14.85 mb groot.

 

U ontvangt de handleiding per email binnen enkele minuten. Als u geen email heeft ontvangen, dan heeft u waarschijnlijk een verkeerd emailadres ingevuld of is uw mailbox te vol. Daarnaast kan het zijn dat uw internetprovider een maximum heeft aan de grootte per email. Omdat hier een handleiding wordt meegestuurd, kan het voorkomen dat de email groter is dan toegestaan bij uw provider.

Stel vragen via chat aan uw handleiding

Stel uw vraag over deze PDF

loading

Uw handleiding is per email verstuurd. Controleer uw email

Als u niet binnen een kwartier uw email met handleiding ontvangen heeft, kan het zijn dat u een verkeerd emailadres heeft ingevuld of dat uw emailprovider een maximum grootte per email heeft ingesteld die kleiner is dan de grootte van de handleiding.

Er is een email naar u verstuurd om uw inschrijving definitief te maken.

Controleer uw email en volg de aanwijzingen op om uw inschrijving definitief te maken

U heeft geen emailadres opgegeven

Als u de handleiding per email wilt ontvangen, vul dan een geldig emailadres in.

Uw vraag is op deze pagina toegevoegd

Wilt u een email ontvangen bij een antwoord en/of nieuwe vragen? Vul dan hier uw emailadres in.



Info