SITE PREPARATION
When choosing a site for the spa take into account that its
maintenance and repair works must be carried out behind
the sidewalls, so accessibility and space to walk around the
spa must be ensured.
1. INDOOR/BASEMENT INSTALLATION
If you place your spa indoors, be aware of some special
requirements:
Water may accumulate around the spa, so the flooring mate-
rial must have a proper runoff to avoid accumulation of water.
When building a new room for the spa, constructing a floor
drain is required, or damages may occur due to overflow,
overfilling, or technical failure. Our company does not take
responsibility for any damage in absence of floor drainage.
Humidity will naturally increase in the room where the spa is
located and the evaporated water condenses. For this reason
ensure that the area has proper ventilation. We recommend
installing a dehumidifier in the room.
2. OUTROOR AND PATIO INSTALLATION
A solid horizontal foundation is necessary for installation of
the spa. We advise using a reinforced concrete foundation at
least 10-15cm thick.
Ensure that your deck or foundation will support your spa.
You must know the maximal load capacity of the foundation.
Consult a qualified building contractor or structural engineer.
To find out the weight of your spa, its contents and occupants
please refer to the spa specification chart. This weight must
not exceed the structure’s rated capacity per square meter,
otherwise serious structural damages could result. If you
install the spa outdoors, we recommend a reinforced hori-
zontal concrete pad at least 10-15cm thick.
Install floor drains around your spa to lead water away even
in heavy rain.
When constructing the water drain it is advised to form a 10-
15cm deep sloping ditch around the spa which directs water
to the drain. Water from the drain must be directed to the
canal or a drainage with enough capacity.
Warning: Do not expose the spa to direct sunlight (not even
empty) without proper coverage. The insulated spa cover
preserves the water temperature and provides protection from
sunlight and rain. When exposed to sunshine for a longer period
it may damage the surface of the spa and the spa equipment.
Acrylic rapidly absorbs heat from sun rays, thus reaches a
very high surface temperature which may damage the spa.
In case of sealed design, if the spa was placed between glass
structures, prevent the sun rays from reaching the spa direct-
ly through the glass as the temperature may get too high.
3. IN-GROUND / SUNKEN SPA
In case of sinking the spa into the ground you must make
sufficient space for walking around the spa. For completion
of maintenance works a minimum of 60cm wide inspection
pit must be built around the spa.
The inspection pits bottom must be under the bearing pont
of the spa so that water can flow into the pit in case of water
leakage. A floor drain or sump pump should be used at the
bottom of the pit to ensure continual water drainage.
In case of sinking the spa only the portion below the spa’s
acrylic edge can be sunk. The air of the inspection pit steams
up. To prevent unpleasant odors proper ventilation must be
provided (e.g. installing ventilators). The costs of pulling the
spa out of the ground are borne by the user. If the aforemen-
tioned conditions are not present, setting up the spa may fail.
First filling of the spa
Proper filling of the spa is an important task both technically
and chemically. We advise installation and periodic mainte-
nance by the servicing professionals, which includes inspec-
tion and refilling of spa water. Spas do not contain water
softener and hard water damages the equipment. Improper
filling of the spa may bring air into the system, which damag-
es the heating wire and engines. Pure stream WE00067 (water
softener) and Pure fill WE00068 (carbon filter) are ensured for
your spa. Please fill your spa exclusively through this filters.
Repairs after such failures are not covered by warranty.
Filling process
Remove the spa cover. First remove the cover staves, then
remove the side covers by unscrewing the bottom screws.
During transportation the flare fittings of engines may
dislocate. Check these connections before installation. If
necessary, tighten the flare fittings.
In spas equipped with air engine the flare fitting must be
connected before running the spa for the first time.
Before filling the spa check that the ratchets are not in a
closed state (lever is pulled out and fixed with the safety
lock).
Next fill the spa with water to the sign indicated on its
sidewall.
Filling must be done through the filter housing. Improper
filling can damage the engines and heating element.
Insert the filter or filter cartridges when proper water level
is reached. Be cautious, because when replacing the filter
cartridge air bubbles may remain in the cartridge. To avoid
this the filter cartridges must be tilted in the water to remove
air from them, and only then fitted to their place.
INITIAL INSTALLATION
6
8

Hulp nodig? Stel uw vraag in het forum

Spelregels
1

Forum

Wellis-In.Grid

Zoeken resetten

Misbruik melden

Gebruikershandleiding.com neemt misbruik van zijn services uitermate serieus. U kunt hieronder aangeven waarom deze vraag ongepast is. Wij controleren de vraag en zonodig wordt deze verwijderd.

Product:

Bijvoorbeeld antisemitische inhoud, racistische inhoud, of materiaal dat gewelddadige fysieke handelingen tot gevolg kan hebben.

Bijvoorbeeld een creditcardnummer, een persoonlijk identificatienummer, of een geheim adres. E-mailadressen en volledige namen worden niet als privégegevens beschouwd.

Spelregels forum

Om tot zinvolle vragen te komen hanteren wij de volgende spelregels:

Belangrijk! Als er een antwoord wordt gegeven op uw vraag, dan is het voor de gever van het antwoord nuttig om te weten als u er wel (of niet) mee geholpen bent! Wij vragen u dus ook te reageren op een antwoord.

Belangrijk! Antwoorden worden ook per e-mail naar abonnees gestuurd. Laat uw emailadres achter op deze site, zodat u op de hoogte blijft. U krijgt dan ook andere vragen en antwoorden te zien.

Abonneren

Abonneer u voor het ontvangen van emails voor uw Wellis In.Grid bij:


U ontvangt een email met instructies om u voor één of beide opties in te schrijven.


Ontvang uw handleiding per email

Vul uw emailadres in en ontvang de handleiding van Wellis In.Grid in de taal/talen: Engels als bijlage per email.

De handleiding is 11.71 mb groot.

 

U ontvangt de handleiding per email binnen enkele minuten. Als u geen email heeft ontvangen, dan heeft u waarschijnlijk een verkeerd emailadres ingevuld of is uw mailbox te vol. Daarnaast kan het zijn dat uw internetprovider een maximum heeft aan de grootte per email. Omdat hier een handleiding wordt meegestuurd, kan het voorkomen dat de email groter is dan toegestaan bij uw provider.

Stel vragen via chat aan uw handleiding

Stel uw vraag over deze PDF

loading

Andere handleiding(en) van Wellis In.Grid

Wellis In.Grid Gebruiksaanwijzing - Nederlands - 113 pagina's

Wellis In.Grid Gebruiksaanwijzing - Deutsch - 124 pagina's

Wellis In.Grid Gebruiksaanwijzing - Français - 108 pagina's


Uw handleiding is per email verstuurd. Controleer uw email

Als u niet binnen een kwartier uw email met handleiding ontvangen heeft, kan het zijn dat u een verkeerd emailadres heeft ingevuld of dat uw emailprovider een maximum grootte per email heeft ingesteld die kleiner is dan de grootte van de handleiding.

Er is een email naar u verstuurd om uw inschrijving definitief te maken.

Controleer uw email en volg de aanwijzingen op om uw inschrijving definitief te maken

U heeft geen emailadres opgegeven

Als u de handleiding per email wilt ontvangen, vul dan een geldig emailadres in.

Uw vraag is op deze pagina toegevoegd

Wilt u een email ontvangen bij een antwoord en/of nieuwe vragen? Vul dan hier uw emailadres in.



Info