Technical Appendix - Flues
2. Flue or Chimney
2.1 The flue or chimney system must be in good condition.
It must be inspected by a competent person and passed for
use with the appliance before installation.
Products of combustion entering the room can cause
serious health risks.
2.2 The following must be checked:
The construction of the masonry chimneys, flue block
chimneys and connecting flue pipe system must meet the
requirements of the Building Regulations.
A flexible flue liner system can be used if certified for
use with solid fuel systems and installation complies with
manufacturer’sinstructionsandBuildingRegulations.
The flue liner must be replaced when an appliance is
replaced, unless proven to be recently installed and in
good condition.
If it is necessary to fit a register plate it must conform to
the Building Regulations.
The minimum height of the flue or chimney must be 4.5m
from the hearth to the top of the flue, with no horizontal
sections and a maximum of 4 bends. Bends must have
angles of less than 45 degrees from the vertical.
— There should be at least 600mm of vertical flue pipe
above the appliance before any bends are introduced.
Ensure the connecting flue pipe is kept a suitable
distance from any combustible material and does not
form part of the supporting structure of the building.
— The installer must ensure the flue pipe diameter is not
less than the diameter of the outlet of the appliance and
does not narrow to less than the size of the outlet at any
point in the system.
Make provision to remove the appliance without the need
to dismantle the chimney.
Any existing flue must be confirmed as suitable
for the new intended use as defined in the Building
Regulations.
The flue or chimney systems must be inspected and
swept to confirm the system is structurally sound and
free from obstructions.
If the chimney is believed to have previously served an
open fire it must be swept a second time within a month
of regular use after installation to clear any soot falls that
may have occurred due to difference in combustion levels.
The flue exit from the building must comply with local
building control rules.
— Chimney heights and/or separations may need to
be increased in particular cases where wind exposure,
surrounding tall buildings, high trees or high ground could
have adverse effects on flue draught.
Do not connect or share the flue or chimney system with
another heating appliance.
2.3 Do not connect to systems containing large voids or spaces
over 230mm square.
2.4 Suitable access must be provided to enable the collection
and removal of debris.
2.5 The flue must be swept and inspected when the appliance
is installed.
Flue Draught
The flue draught must be checked with all windows and
doors closed and any extraction fans in this, or adjoining
rooms, running at maximum speed (see Installation
Checklist for ventilation requirements).
Twin Wall Flue System
If this appliance is to be used in conjunction with a twin
wall flue system then Stovax recommend the use of
their Professional XQ range. Details of this product are
available from your Stovax retailer.
In the U.K:
*BS En 15287-1, and the requirements of Building
Regulations
**This should be done by a NACS registered (UK
only)/INFO registered (Eire only) chimney sweep,
who will issue you with a certificate.
Building Regulations Document J
Flue Plate:
Where a hearth, fireplace, flue or chimney is
provided or extended (including cases where a
flue is provided as part of refurbishment work),
information essential to the correct appliance and
use of these should be permanently posted in the
building, to meet Requirement J4 of the Building
Regulations (England and Wales), F3.12 (Scotland).
Additional:
A new factory made system that complies to EN
1856; Part 1 can be used providing installation is
to the requirements of:
i) BS 7566 Parts 1 -4
ii) the manufacturer's instructions
iii) Building Regulations.
For a guide containing information on Chimneys
and Flues contact:
The British Flue & Chimney Manufacturers’
Association,
FETA
2 Waltham Court
Milley Lane
Hare Hatch
Reading
Berkshire RG10 9TH
Tel: 0118 9403416 e-mail: info@feta.co.uk
33

Hulp nodig? Stel uw vraag in het forum

Spelregels

Misbruik melden

Gebruikershandleiding.com neemt misbruik van zijn services uitermate serieus. U kunt hieronder aangeven waarom deze vraag ongepast is. Wij controleren de vraag en zonodig wordt deze verwijderd.

Product:

Bijvoorbeeld antisemitische inhoud, racistische inhoud, of materiaal dat gewelddadige fysieke handelingen tot gevolg kan hebben.

Bijvoorbeeld een creditcardnummer, een persoonlijk identificatienummer, of een geheim adres. E-mailadressen en volledige namen worden niet als privégegevens beschouwd.

Spelregels forum

Om tot zinvolle vragen te komen hanteren wij de volgende spelregels:

Belangrijk! Als er een antwoord wordt gegeven op uw vraag, dan is het voor de gever van het antwoord nuttig om te weten als u er wel (of niet) mee geholpen bent! Wij vragen u dus ook te reageren op een antwoord.

Belangrijk! Antwoorden worden ook per e-mail naar abonnees gestuurd. Laat uw emailadres achter op deze site, zodat u op de hoogte blijft. U krijgt dan ook andere vragen en antwoorden te zien.

Abonneren

Abonneer u voor het ontvangen van emails voor uw Stovax Riva - Woodburning and Multi-fuel bij:


U ontvangt een email met instructies om u voor één of beide opties in te schrijven.


Ontvang uw handleiding per email

Vul uw emailadres in en ontvang de handleiding van Stovax Riva - Woodburning and Multi-fuel in de taal/talen: Engels als bijlage per email.

De handleiding is 5.3 mb groot.

 

U ontvangt de handleiding per email binnen enkele minuten. Als u geen email heeft ontvangen, dan heeft u waarschijnlijk een verkeerd emailadres ingevuld of is uw mailbox te vol. Daarnaast kan het zijn dat uw internetprovider een maximum heeft aan de grootte per email. Omdat hier een handleiding wordt meegestuurd, kan het voorkomen dat de email groter is dan toegestaan bij uw provider.

Stel vragen via chat aan uw handleiding

Stel uw vraag over deze PDF

loading

Uw handleiding is per email verstuurd. Controleer uw email

Als u niet binnen een kwartier uw email met handleiding ontvangen heeft, kan het zijn dat u een verkeerd emailadres heeft ingevuld of dat uw emailprovider een maximum grootte per email heeft ingesteld die kleiner is dan de grootte van de handleiding.

Er is een email naar u verstuurd om uw inschrijving definitief te maken.

Controleer uw email en volg de aanwijzingen op om uw inschrijving definitief te maken

U heeft geen emailadres opgegeven

Als u de handleiding per email wilt ontvangen, vul dan een geldig emailadres in.

Uw vraag is op deze pagina toegevoegd

Wilt u een email ontvangen bij een antwoord en/of nieuwe vragen? Vul dan hier uw emailadres in.



Info