36 GMC-I Messtechnik GmbH
15 Measurements in Accordance with National and
International Standards with Selector Switch in Auto Position
If measurements need to be performed in accordance with given stan-
dards which require specific tests, and if results need to be stored and
documented with a test report, an automatic test sequence is advisable
instead of individual measurements.
Note
+
for tests per EN 60950, EN 61010 and EN 60335
The DUT must be connected to the test socket for the automatic
test sequence! The DUT must comply with safety class I or II.
õ Connect the test instrument to mains power.
A mains connection test is initialized (see chapter 3.2 on page 12).
õ
Connect the DUT to the test socket at the test instrument (see
chapter 7 on page 17). The test instrument initializes
connection type recognition
.
õ Set the selector switch to the Auto position. If the DUT has been con-
nected to the test socket, safety class recognition is performed. Other-
wise, the safety class must be specified manually. In the initial program
window, move the cursor up with the
key into the third line and ac-
knowledge with the key. A safety class can now be selected with
the
and keys and acknowledged with the key.
õ In order to select the regulation for which testing is to be performed,
move the cursor up within the initial program window with the
key
into the top line and acknowledge with the key. The desired stan-
dard can now be selected with the
and keys and acknowledged
with the key. If you always want to test in accordance with a spe-
cific standard, this can be stored as the default standard in the setup
menu. Otherwise, the selected standard only remains active until the
test instrument is disconnected from mains power (factory default set-
ting: VDE 0701-0702).
õ The test sequence can be configured in the Setup menu, limit values
can be changed if necessary and database options can be configured.
õ The test sequence is started by selecting Start test and by acknowledg-
ing with the key (see “Test Sequences”).
Tests which have already been included in chapters 9 through 14 are not
described here again. The only exception is measurement of extension
cables.
15.1 Test Sequences
Test sequences for the various standards are always run in the same
order, assuming that the device under test has been properly connected
and the mains connection test has been passed.
The test sequence can be run step by step with manual activation of each
subsequent step if this function has been specified, or automatically. Step
by step manual operation can be selected in the initial program window in
the setup menu under “Sequence” ... “manual sequence”.
Safety class: SC I or SC II is automatically recognized by the test instru-
ment. If the safety class is not correctly recognized, you can change it
manually. This manual correction is not stored however.
Visual inspection: If “visual inspection” has been activated
in the initial program window under “Sequence”.
If a part is recognized as defective by the user, it must be identified as
such by selecting it with the cursor and acknowledging with the key.
Protective conductor resistance measurement
(for SC I devices under test only)
Note
+
This test cannot be skipped. Exception:
This measurement can be skipped by pressing
(when mes-
sage „Connect probe to protective conductor“ is displayed) if a
protective conductor connection is not possible.
Evaluation of protective conductor testing
High-voltage test for DIN VDE 0701 Part 1, Appendix E, EN 60950,
EN 61010, EN 60335, EN 60601, if selected in the setup menu.
Insulation resistance measurement
IEC 62353: only if selected in the setup menu of the
initial program window under “Sequence ...
EN 60601: only if selected in the initial program window
under „Test Conditions“
DIN VDE 0701-0702 only if R-INS is activated in the initial program
window
Evaluation of insulation test
Leakage current measurement (various single-fault conditions are run de-
pending on classification)
Evaluation of each individual leakage current measurement, see also
chapter 21.2
Evaluation of the overall test
36

Hulp nodig? Stel uw vraag in het forum

Spelregels

Misbruik melden

Gebruikershandleiding.com neemt misbruik van zijn services uitermate serieus. U kunt hieronder aangeven waarom deze vraag ongepast is. Wij controleren de vraag en zonodig wordt deze verwijderd.

Product:

Bijvoorbeeld antisemitische inhoud, racistische inhoud, of materiaal dat gewelddadige fysieke handelingen tot gevolg kan hebben.

Bijvoorbeeld een creditcardnummer, een persoonlijk identificatienummer, of een geheim adres. E-mailadressen en volledige namen worden niet als privégegevens beschouwd.

Spelregels forum

Om tot zinvolle vragen te komen hanteren wij de volgende spelregels:

Belangrijk! Als er een antwoord wordt gegeven op uw vraag, dan is het voor de gever van het antwoord nuttig om te weten als u er wel (of niet) mee geholpen bent! Wij vragen u dus ook te reageren op een antwoord.

Belangrijk! Antwoorden worden ook per e-mail naar abonnees gestuurd. Laat uw emailadres achter op deze site, zodat u op de hoogte blijft. U krijgt dan ook andere vragen en antwoorden te zien.

Abonneren

Abonneer u voor het ontvangen van emails voor uw Gossen Metrawatt SECULIFE ST HV bij:


U ontvangt een email met instructies om u voor één of beide opties in te schrijven.


Ontvang uw handleiding per email

Vul uw emailadres in en ontvang de handleiding van Gossen Metrawatt SECULIFE ST HV in de taal/talen: Engels als bijlage per email.

De handleiding is 0,91 mb groot.

 

U ontvangt de handleiding per email binnen enkele minuten. Als u geen email heeft ontvangen, dan heeft u waarschijnlijk een verkeerd emailadres ingevuld of is uw mailbox te vol. Daarnaast kan het zijn dat uw internetprovider een maximum heeft aan de grootte per email. Omdat hier een handleiding wordt meegestuurd, kan het voorkomen dat de email groter is dan toegestaan bij uw provider.

Stel vragen via chat aan uw handleiding

Stel uw vraag over deze PDF

loading

Uw handleiding is per email verstuurd. Controleer uw email

Als u niet binnen een kwartier uw email met handleiding ontvangen heeft, kan het zijn dat u een verkeerd emailadres heeft ingevuld of dat uw emailprovider een maximum grootte per email heeft ingesteld die kleiner is dan de grootte van de handleiding.

Er is een email naar u verstuurd om uw inschrijving definitief te maken.

Controleer uw email en volg de aanwijzingen op om uw inschrijving definitief te maken

U heeft geen emailadres opgegeven

Als u de handleiding per email wilt ontvangen, vul dan een geldig emailadres in.

Uw vraag is op deze pagina toegevoegd

Wilt u een email ontvangen bij een antwoord en/of nieuwe vragen? Vul dan hier uw emailadres in.



Info