EN-8 452168.66.05a · FD 0104 www.glendimplex.de
English HPL 9S-TU(R)W - HPL 18S-TU(R)W
7.3 Electrical connection
3 lines/cables must be routed to the heat pump in total:
A standard 5-core cable is used to connect the heat pump
to the power supply.
The cable must be provided on-site. The conductor cross
section is selected in accordance with the power con-
sumption of the heat pump (see attachment Device Infor-
mation) and the applicable VDE (EN) and VNB regulations.
An all-pole disconnecting device with a contact gap of at
least 3 mm (e.g. utility blocking contactor or power contac-
tor) must be installed in the heat pump power supply.
A 3-pole circuit breaker with joint tripping of all outer con-
ductors (trip current in accordance with device informa-
tion) provides the short circuit protection taking into ac-
count the layout of the internal wiring.
The relevant components in the heat pump contain an in-
ternal overload protection.
When connecting, ensure that the incoming supply has a
clockwise rotating field.
Phase sequence: L1, L2, L3.
CAUTION!
!
!
Ensure that there is a clockwise rotating field: With incorrect
wiring the starting of the heat pump is prevented. A
corresponding warning is indicated on the display of the heat
pump manager (adjust wiring).
The control voltage is supplied via the heat pump manager.
A 3-pole line must be laid for this in accordance with the
electrical documentation. Further information on the wir-
ing of the heat pump manager is available in the heat pump
manager operating instructions.
A shielded communication line(J-Y(ST)Y ..LG) (not included
in the scope of supply) connects the heat pump manager
with the µPC2 installed in the heat pump. More detailed in-
structions can be found in the heat pump manager operat-
ing instructions and in the electrical documentation.
NOTE
º
ºººº
The communication cable is necessary for the function of air-
to-water heat pumps in outdoor installation. It must be
shielded and laid separately from the mains cable.
7.3.1 Demand sensor connection
The demand sensor R2.2 (NTC 10) is included with the heat
pump manager. It must be installed depending on the hydrau-
lics used (see Appendix Chapter 3 on p. XI).
If a demand sensor is not connected, the second heat genera-
tor can not be controlled with the heat pump manager in the
event of an interruption in communication either.
NOTE
º
ºººº
The return sensor R2 installed in the heat pump is active when
the compressor is running and must not be disconnected.
8 Commissioning
8.1 General
To ensure that commissioning is performed correctly, it should
only be carried out by an after-sales service technician author-
ised by the manufacturer. This may be a condition for an addi-
tional warranty (see "Warranty service").
8.2 Preparation
The following items must be checked prior to commissioning:
All of the heat pump connections must be installed as de-
scribed in Chapter 7.
All valves which could impair the proper flow of the heating
water in the heating circuit must be open.
The air intake and air outlet paths must be clear.
The fan must turn in the direction indicated by the arrow.
The settings of the heat pump manager must be adapted
to the heating system in accordance with the latter's op-
erating instructions.
Ensure that the condensate drain functions properly.
8.3 Procedure
The heat pump is commissioned via the heat pump manager.
Settings should be made in compliance with the HPM's instruc-
tions.
At heating water temperatures below 7 °C, commissioning is
not possible. The water in the buffer tank must be heated with
the second heat generator to at least 18 °C.
To ensure problem-free commissioning, the following proce-
dure is to be implemented:
1) Close all consumer circuits.
2) Ensure that the heat pump has the correct water flow.
3) Use the manager to select the automatic operating mode.
4) In the special functions menu, start the "Commissioning"
program.
5) Wait until a return temperature of at least 25 °C has been
reached.
6) Now slowly reopen the heating circuit valves in succession
so that the heating water flow rate is constantly raised by
slightly opening the respective heating circuit. The heat-
ing water temperature in the buffer tank must not be al-
lowed to drop below 20 °C during this process. This en-
sures that the heat pump can be defrosted at any time.
7) When all heating circuits are fully open and a return tem-
perature of at least 18 °C is maintained, the commissioning
is complete.
CAUTION!
!
!
Operating the heat pump at low system temperatures may
cause the heat pump to break down completely.
32

Hulp nodig? Stel uw vraag in het forum

Spelregels

Misbruik melden

Gebruikershandleiding.com neemt misbruik van zijn services uitermate serieus. U kunt hieronder aangeven waarom deze vraag ongepast is. Wij controleren de vraag en zonodig wordt deze verwijderd.

Product:

Bijvoorbeeld antisemitische inhoud, racistische inhoud, of materiaal dat gewelddadige fysieke handelingen tot gevolg kan hebben.

Bijvoorbeeld een creditcardnummer, een persoonlijk identificatienummer, of een geheim adres. E-mailadressen en volledige namen worden niet als privégegevens beschouwd.

Spelregels forum

Om tot zinvolle vragen te komen hanteren wij de volgende spelregels:

Belangrijk! Als er een antwoord wordt gegeven op uw vraag, dan is het voor de gever van het antwoord nuttig om te weten als u er wel (of niet) mee geholpen bent! Wij vragen u dus ook te reageren op een antwoord.

Belangrijk! Antwoorden worden ook per e-mail naar abonnees gestuurd. Laat uw emailadres achter op deze site, zodat u op de hoogte blijft. U krijgt dan ook andere vragen en antwoorden te zien.

Abonneren

Abonneer u voor het ontvangen van emails voor uw Dimplex HPL 9S-TURW bij:


U ontvangt een email met instructies om u voor één of beide opties in te schrijven.


Ontvang uw handleiding per email

Vul uw emailadres in en ontvang de handleiding van Dimplex HPL 9S-TURW in de taal/talen: Duits, Engels, Frans als bijlage per email.

De handleiding is 2.27 mb groot.

 

U ontvangt de handleiding per email binnen enkele minuten. Als u geen email heeft ontvangen, dan heeft u waarschijnlijk een verkeerd emailadres ingevuld of is uw mailbox te vol. Daarnaast kan het zijn dat uw internetprovider een maximum heeft aan de grootte per email. Omdat hier een handleiding wordt meegestuurd, kan het voorkomen dat de email groter is dan toegestaan bij uw provider.

Stel vragen via chat aan uw handleiding

Stel uw vraag over deze PDF

loading

Uw handleiding is per email verstuurd. Controleer uw email

Als u niet binnen een kwartier uw email met handleiding ontvangen heeft, kan het zijn dat u een verkeerd emailadres heeft ingevuld of dat uw emailprovider een maximum grootte per email heeft ingesteld die kleiner is dan de grootte van de handleiding.

Er is een email naar u verstuurd om uw inschrijving definitief te maken.

Controleer uw email en volg de aanwijzingen op om uw inschrijving definitief te maken

U heeft geen emailadres opgegeven

Als u de handleiding per email wilt ontvangen, vul dan een geldig emailadres in.

Uw vraag is op deze pagina toegevoegd

Wilt u een email ontvangen bij een antwoord en/of nieuwe vragen? Vul dan hier uw emailadres in.



Info